Commisioning of the biggest GIS Transformer Station of Türkiye Electricity Transmission Network CO.

Commisioning of the biggest GIS Transformer Station of Türkiye Electricity Transmission Network CO.5.07.2018

We're taking pride in commisioning the biggest GIS Transformer Station of Türkiye Electricity Transmission Network CO.

 

380/154/33 kV Deliklikaya GIS Transformer Station

İstanbul Europe Side TEİAŞ 1. Regional Directorate

 

Contract Reference:        DB.ATT.19

 

154kV Feeder Number:    10 line / cable feeders

    2 154kV/33kV 100MVA Transformer Feeder

    3 380kV/154kV 250MVA Autotransformer Feeder

    Coupling Feeder consisted of 4 bus bars combination

 

380kV Fider Sayısı    :      10 line feeders

                                           3 380kV/33kV 125MVA Transformer Feeder

                                           3 380kV/154kV 250MVA Autotransformer Feeder

                                           Coupling Feeder

 

KESİR Scope of Project:

Secondary Project Design

Production of 380kV CRP (Control Relay Panels) and LCC (Local Control Panels)

Production of 154kV CRP (Control Relay Panels) and LCC (Local Control Panels)

Turnkey Test and Commissioning

Turnkey Installation

 

Scope of Turnkey Test and Commissioning

Setting up substructure of Protection Relays and Bay Control Units

IEC61850 substructure and GOOSE configuration

380kV & 154kV & 33kV Bay Control Unit Function Test

380kV & 154kV & 33kV Relay Protection Function Test

380kV & 154kV & 33kV Primary and Secondary Tests

380kV GIS High Voltage Tests

154 kV GIS High Voltage Test

Earth Resistance Tests

 

Scope of Turnkey Installation

380kV GIS Installation

154kV GIS Installation

Production of Medium Voltage Cable Head

Earthing

Installation of Steel, Line and Air Insulated Switchyard Primary Equipment

All Signals and  LV, MV Energy Cabling